Millie and Severson completed the 1st parking deck of the 4 story, 75k sf Manhattan Beach Medical Office Building. The photo shows a 53-meter boom pump handling the 25,000 sf concrete pour on the post-tension deck. Accomplished in one day with an orchestra of 46 trucks, 31 workers and 690 cubic yards of concrete. The project is anticipated to be complete in September 2016.